Where should we start?
Ashford Landing, Plan and Unit Variance
38 lots · 22 closed · 16 active · Generated from the job cost ledger
Back to chat
Export
Send to Dana
Lot 42, Plan 2260
$3,343
Net variance over. 32nd of 38.
Community average
$1,480
Over, across all 38 lots
Plan 2260 average
$2,880
Over, across 11 lots
All other plans
$910
Over, across 27 lots
All 38 lots by net variance Low to high
Community average $1,480
Lot 42, $3,343
Lot 17, bestLot 29, worst
Average variance by plan Dollars over
Plan 1980
$310
Plan 2050
$640
Plan 2110
$1,240
Plan 2185
$1,970
Plan 2260
$2,880
Lot 42, where the money went Cost codes with variance. All other codes at budget.
| Cost code | Budget | Actual | Variance | Billable to buyer | Cause |
|---|---|---|---|---|---|
| 03100 Framing labor | 18,400 | 20,400 | +2,000 | No | Return crew and trim standby, frame inspection hold |
| 15400 Plumbing rough | 9,850 | 13,373 | +3,523 | Partial | CO-114 pool bath $2,180 billed · CO-119 drain $1,343 not billed |
| 03300 Concrete flatwork | 11,200 | 11,200 | 0 | n/a | At budget |
| 16100 Electrical rough | 8,600 | 8,600 | 0 | n/a | At budget |
| Net unbilled variance | +3,343 | $2,180 recovered at closing |
Lot 42 schedule Day 48 of a 74 day target. Two days behind.
Day 0
Form boards
Form boards
Day 31 to 34
Frame inspection hold
Frame inspection hold
Day 48
Today
Today
Day 74
Target CO
Target CO
Hold cost3 days
Recovered1 day
Net position2 days behind
Community average cycle71 days
Plan 2260 exposure Same slab dimension, same drain relocation
Lot 08
Lot 12
Lot 19
Lot 24
Lot 29
Lot 33
Lot 37
Lot 42
Lot 47
Lot 51
Lot 55
Lots affected4 of 11
Unbilled to date$5,372
Starts in next 45 days7 homes
Projected if unchanged$9,400
Best unit
Lot 17, Plan 1980
$410 under budget, 66 days form boards to CO.
Worst unit
Lot 29, Plan 2260
$4,905 over budget, 78 days. Same drain relocation.
Recommended action
Correct the Plan 2260 slab dimension before the next release.
The drain lands under a bearing wall because the slab sheet does not match the framing layout. Four of the five worst units in the community are Plan 2260. Seven homes start in the next 45 days.
Flag plan sheet to Dana
Rebudget remaining releases
Open CO-119